Planning - Production Schedule

Production Schedule

I am going to specify the production dates and what we will complete on each date. I will include details such as editing and recording.


Filming Start: Monday 8th February 2010
On our first filming session, we will get the main establishing shots and the main scenes recorded.
We have chosen this date because this is the date when cameras are available for filming.

Additional Filming: Monday 15th February 2010
On our second filming session, we will gather all the other shots which we need such as CCTV footage and scenery shots.

Editing Start: Monday 22nd February 2010
During this editing session, we will split the clips up and cut out unwanted bits of video. We will then arrange in order for the next editing session.

Second Editing Session: Tuesday 23rd February 2010
In this session we will start to trim the clips down and apply effects for CCTV and slow motion. We will hope to have the video in one whole piece by the end.

Third Editing Session: Monday 29th February 2010
For this editing session, we plan to put the audio track we have acquired called “Dubstep Warz” by D1. We will then sync the song to the video and make sure it fits.

Final Editing Session: Tuesday 30th February 2010
By the end of this session we hope to have the video completed along with all transitions and effects. We will then render and export the video to upload.